Still on target for July 29 finish

 
12/07/2019 @ 02:58

The long awaited return for the back road to revert back to two-way traffic is still on target for the end of the month.

Town clerk, Robert Robinson, has released the following update on behalf of the contractors.

·      Works to Bron y Buckley junction completed by Monday

·      Works to Jehu Road/Brook Street junction completed by July 29.

·      Works to Union Street to continue - completion no later than July 29

·      Works to Church Bank completed

·      Works to junction by NFU and into Church Street – commenced, with completion no later than July 29

·      Narrowing of carriageway and widening of paths by Town Hall - starting Monday (possible if weather good Sunday) - completion by July 29

·      Jehu Road/High Street juction - continuing works, completion no later than July 29

·      Re-opening of Brook Street/Union Street along its full length to two-way traffic by July 29

Signage and lining alterations will continue as the works come to an end. This will include double yellow lines extended by Dol Y Felin.